The tower crane It is the go-to lifting equipment for construction sites and other industrial applications where both horizontal and vertical reach are required. Its use on a construction site entails technical, documentation, and operator qualification requirements that the safety officer must be aware of prior to assembly. 

What is a tower crane, and what is it used for on a construction site?

One tower crane It is a stationary lifting device consisting of a vertical structure (tower) and a horizontal element (boom) that allows loads to be moved within a specific operating radius. It is used in the construction of buildings, infrastructure, and industrial plants to lift heavy materials—rebar, formwork, precast concrete, machinery—to great heights with precise positioning. Its installation requires a technical design, administrative authorization, and supervised commissioning. 

Parts of a tower crane

🏗️ Parts of a tower crane
Click on each item to see its function and the associated risks
T P CP CT CR G
👆 Click on any element in the diagram to see its function and the associated risks.
T · Tower
P · Pen
CP · Counterblade
CT · Counterweight
CR · Cart
G · Hook
A general schematic diagram of a top-slewing tower crane. Proportions and components may vary depending on the manufacturer and model.

The main elements are the tower (vertical lattice structure), the pen (horizontal working arm), the counterblade (the opposite arm that houses the motor and the wires), the counterweight (concrete or steel masses that balance the load), the car (a moving part that runs along the boom and from which the hook hangs) and the hook with its anti-fall safety device. The crane operator's cab can be located at the top of the tower or be a ground-level cab with remote control. 

Types of tower cranes: base-slewing, top-slewing, and self-expanding

The three main types differ in the location of the rotating mechanism and in their mounting system: 

Type Turn Assembly Typical Use Scope
Turn on the tip Only the upper part (pen + counterpen) Section by section using an auxiliary crane Residential and Commercial Construction Up to 70 m in radius
Base Turn The entire tower It requires more floor space Industrial Projects and Major Infrastructure Projects Up to 80 m in radius
Self-expanding Up front Self-erecting: can be assembled without an auxiliary crane Small and medium-sized construction projects, urban renewal Up to 40 m in radius

The self-erecting tower crane It has become increasingly popular in smaller-scale projects due to its ability to be assembled and disassembled without auxiliary equipment, thereby reducing the time required to put it into service. 

Installation, Commissioning, and Dismantling: Phases and Responsible Parties

The tower crane assembly It is one of the highest-risk operations on a construction site. The process includes: preparing the assembly project by a qualified technician, notification to the regional industrial authority, installation by an authorized installation company, pre-commissioning inspection by an authorized regulatory agency (ARA) and issuance of the installation certificate. 

The Dismantling of a tower crane It follows the reverse process and also requires technical supervision. Both assembly and disassembly must be carried out within the cordoned-off area and under the direction of a responsible technician. For more information on the safety coordinator’s responsibilities during these phases, see our articles on the Regulation No. 1627/1997 on Construction Projects and the Machinery Regulations. 

Applicable Regulations and Required Documentation

The main regulation is the RD 836/2003, which approves the ITC MIE-AEM-2 on tower cranes for construction sites or other applications (in effect, last updated in September 2025). This instruction establishes the requirements for design, manufacture, assembly, commissioning, maintenance, and periodic inspection, as well as the requirements for the operator. 

The required documentation includes the assembly project, the instruction manual from the manufacturer, the installation certificate (Annex VI of Royal Decree 836/2003), the records of periodic inspections and the maintenance log. All of this documentation must be available on-site throughout the facility's service life. 

Carnet Crane Operator: Requirements for Becoming a Tower Crane Operator

The crane operator's license It is mandatory to have this certification to operate a tower crane in Spain. It is regulated by the RD 836/2003 (Annex VI) and is valid throughout the country. The requirements for obtaining it are: 

  • To Be of legal age 
  • Overcoming a medical exam which assesses vision, balance, orientation, hearing, and psychological aptitudes 
  • Demonstrate your knowledge through one of the following methods: an ESO diploma plus a theoretical and practical course of at least 200 hours (50 theory hours + 150 practical hours) and an official exam; vocational training diploma or certificate of professional competence; certification from an accredited organization in accordance with UNE-EN ISO 17024; or a recognized qualification from another EU member state 

The card has a valid for 5 years and is renewed for equal periods upon certification. The certificate is issued by the competent authority of the autonomous community where the application is processed. 

Most Common Risks and Safety Measures

The risks associated with tower cranes There are three most serious ones: 

  • Rollover due to overloading, improper installation, or insufficient foundation. The maximum peak load must be strictly observed; a load moment limiter is a mandatory safety device. 
  • Wind on a tower crane: the wind It is the most underestimated risk. Royal Decree 836/2003 establishes the criteria for maximum operating speed (usually 72 km/h) and the facility’s safety limits. When winds exceed the operating limit, the crane must remain in weather vane (free-swinging boom that rotates with the wind) and unloaded. The crane operator must be familiar with the installed anemometers and the shutdown procedure. 
  • Load Drop: due to a broken hook, a failure of the anti-fall device, or improper slinging. The area beneath the boom must be marked off and kept clear of personnel during lifting operations. 

Servicing, Maintenance, and Periodic Inspections

The tower crane maintenance includes daily inspections by the crane operator (condition of the hook, cables, limiters, and brakes), periodic preventive maintenance by a specialized company, and regulatory inspections by OCA. Royal Decree 836/2003 establishes the frequency of these inspections based on the crane's age and use. All records must be entered in the maintenance log and be maintained throughout the equipment's service life. 

Training for Construction Crews: Prevention and Management in Construction 

Safety in the use of tower cranes is part of a broader strategy to Prevention Management on Construction Sites. Educa PHAROS offers training in Occupational Safety and Health in Construction and in BIM and Construction Management For technicians, safety coordinators, and site managers who need to master both the regulatory and operational aspects of this type of equipment. 

For information on the framework for coordinating activities among companies on a construction site, see also our article on coordination of business activities and the article about shallow foundations. 

Frequently Asked Questions About Tower Cranes

What is the maximum wind speed a tower crane can withstand?

The standard operating limit is 72 km/h (20 m/s), although the manufacturer may specify lower values depending on the model. Above that threshold, the crane operator must stop operations, set the load down, and leave the boom in wind vane position. The structure's survival speed—with the crane out of service and in the "weather vane" position—is significantly higher and is calculated in the installation design. 

How often is a tower crane inspected?

The regulatory inspections OCA inspections are conducted based on the age of the equipment: generally, every 4 years for cranes less than 10 years old and every 2 years for older cranes, although Royal Decree 836/2003 and the relevant autonomous community may establish stricter timeframes. Preventive maintenance inspections by a specialized company are separate and must be performed at the intervals specified by the manufacturer in the instruction manual. 

Find out what's new in our newsletter

Knowledge, innovation, and training to keep moving forward together.

Related Articles

The tower crane is the standard lifting equipment used on construction sites and in other industrial applications where it is

TIG (Tungsten Inert Gas) welding, also known as GTAW (Gas Tungsten Arc Welding), is an arc welding process

The industrialized housing sector in Spain has grown at annual rates ranging from 12% to 20%.

Scroll to Top
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.